Audax begins construction of 22 MWp from its solar generation portfolio

Corporate Strategy Generation Projects
  • With an investment of approximately 16 million euros, the Cuatro Caminos 1, Cuatro Caminos 2, Cuatro Caminos 3, and Cuatro Caminos 4 projects will have a total capacity of 21.87 MWp.

  • The future projects are located in the municipality of Cabanillas del Campo, in the province of Guadalajara.

 

DECEMBER 28, 2022.– Audax, an energy group with a presence in nine countries, has announced the start of construction for four photovoltaic projects located in the municipality of Cabanillas del Campo, in the province of Guadalajara, which will have a total capacity of 21.87 MWp.

In line with its strategy to continue promoting its generation activity through the various projects that make up its portfolio, Audax plans to invest approximately 16 million euros in their construction.

The project will feature 39,489 modules of 550 Wp with Tier-1 category single-axis trackers, which will allow for the generation of 40.5 GWh/year.

This installation will connect to the Cabanillas del Campo Substation via its own evacuation line of just over 5 kilometers. The construction period is estimated to be approximately 1 year, as it includes a biological shutdown period from March to June. The company ensures the supervision of the works with top-tier contractors who meet high quality standards under the EPC (turnkey) contract modality.

For the construction of the aforementioned projects, the Group is in a very advanced stage of negotiations to secure appropriate financing. This will be non-recourse financing, following the same structure as other previous projects in the generation portfolio.

Audax currently has 226 MW of installed capacity and 19.2 MWp in the commissioning phase, relating to the La Miranda and Zaratán 1 and 2 photovoltaic projects.