Audax Commissions the Carolinas I and II Photovoltaic Plants
Audax, an energy group operating in nine countries, has obtained operational authorization from the Provincial Delegation for Sustainable Development of Guadalajara to commission the Carolinas I and II photovoltaic plants in the municipality of El Casar, Guadalajara province (Castilla-La Mancha). With a total capacity of 10 MWp, the plants have also begun feeding energy into the grid.
It is worth noting that the Cañamares photovoltaic plant in the municipality of Fontanar, Guadalajara province (Castilla-La Mancha), with a capacity of 5 MWp, has already been operational for several weeks, feeding its generated power into the grid and expanding the Group’s portfolio of operating facilities.
Both the Carolinas I and II photovoltaic plants and the Cañamares project will sell their energy under a PPA contract to their parent company, Audax Renovables.
Due to ongoing conditions caused by the COVID-19 pandemic, certain administrative procedures before various institutions experienced delays. However, these delays have been resolved, leading to the successful commissioning of the aforementioned facilities.
Additionally, the Group continues with the construction of the following projects:
– La Zarzuela I, II, III, and IV, located in the municipality of Escalonilla, Toledo, with a total capacity of 20 MWp.
– Las Alberizas I, II, III, and IV, located in the municipality of Torija, Guadalajara, with a total capacity of 20 MWp.
– Calañas, a project located in the municipality of the same name in Huelva, with a capacity of 4.48 MWp.
– Los Arenales, located in Polán, Toledo, with a capacity of 5 MWp.
Construction of the aforementioned projects is progressing normally, and the Group expects them to be completed and commissioned during the current financial year.
None of the aforementioned projects required third-party financing, as they were funded through the green bond issuances secured by the Group at the end of the previous financial year.
Over the coming weeks, the Group will continue to keep the market duly informed of progress on the projects in its portfolio, with the aim of keeping the market and its investors continuously informed.