Audax commissions the 20 MWp La Zarzuela photovoltaic plants in Toledo

Corporate Strategy Generation Projects

Continuing to drive its generation business, and following receipt of the commissioning certificate, the company will begin operations at the La Zarzuela I, II, III and IV photovoltaic plants in Castilla-La Mancha.

 

Audax, an energy group with a presence in nine countries, has obtained from the Toledo Provincial Delegation for Sustainable Development the operating authorisation to bring the La Zarzuela I, II, III and IV photovoltaic plants into service, located in the town of Escalonilla, in the province of Toledo (Castilla-La Mancha), with a total capacity of 20 MWp, and will also imminently begin feeding energy into the grid.

The works have, in fact, been 100% completed for weeks, but some administrative procedures have been delayed at the various institutions involved. Nevertheless, these delays have been resolved, and the imminent start-up of the aforementioned facilities is expected.

In this same regard, it should be noted that the Las Alberizas I, II, III and IV photovoltaic plants, located in the municipality of Torija (Guadalajara), with a total installed capacity of 20 MWp, are in a similar situation to the project referred to above, and are also expected to obtain the corresponding operating authorisation in the coming days, enabling them to begin operations shortly. Once the company obtains the required operating authorisation, it will duly inform the market accordingly.

In addition, it should be noted that the Group continues with the construction and commissioning of the following projects:

  • Calañas, a project located in the Huelva town of the same name, with a capacity of 4.48 MWp.
  • Los Arenales, located in the town of Polán, Toledo, with a capacity of 5 MWp.
  • El Toconal, located in the town of Navalmorales, Toledo, with a capacity of 5 MWp.

Construction of the aforementioned projects is progressing normally, with average completion reaching 90%, and the Group expects them to be completed and brought into operation during the current financial year.

Over the coming weeks, the Group will continue to keep the market duly informed of progress on the projects in its portfolio, with the aim of keeping the market and its investors continuously informed.